Back Porch Progress – 2014 May

We’ve had some progress in May 2014 on the┬áback porch.

Back Porch Status

  The boards for our originally design deck between the kitchen and laundry room have been built. The carpenters will be working on the side floor beams and the loft deck next.

Under Roof

Caution Construction Area

Walls and Flooring

Basement Excavation 2013 Aug 22

Basement Excavation 2013 Aug 21

Basement Excavation 2013 Aug 20

Site Preparation

Site Staking

In July 2013, our site was little more than stakes in the ground among the trees.